LQ-RRTO Rotary heat-storage high-temperature incineration equipment
Cat:Equipment
Overview Of Tower-Type RTO Our company offers two types of rotary RTO, which are the rotary RTO and the single barrel multi-valve RTO. The rotary RTO,...
See Details1. On-site Infrastructure Preparation
The foundation of the Vocs Organic Waste Gas Treatment Engineering Equipment must meet the design load-bearing requirements. Supporting facilities such as power supply, water supply, compressed air, and fuel must be in place and have passed acceptance testing in advance.
Sufficient space should be reserved on-site for ventilation and exhaust ducts to ensure smooth and safe waste gas inlet and outlet.
2. Process and Safety Assessment
Before installation, on-site testing of the exhaust gas composition, concentration, and temperature must be completed to confirm the absence of high concentrations of halogens, sulfides, or other substances that could poison the catalyst.
Fire prevention, explosion-proof valves, and emergency shutdown devices must be installed according to the "Three-Bed RCO Regenerative Catalytic Combustion Technology Standard" to ensure the system can automatically cut off fuel and activate safety valves in abnormal situations.
3. Equipment Arrival Inspection and Pre-commissioning
Upon arrival, all equipment must undergo a visual inspection, checking for specifications and the integrity of key components (such as fans, valves, and sensors) to confirm the absence of transportation damage.
Basic commissioning must be performed, including fan frequency conversion control, temperature sensor calibration, and linkage testing of online differential pressure and concentration monitoring instruments, to ensure the control system can operate automatically.
4. Formal Commissioning and Acceptance Process
After installation, a "preliminary equipment acceptance" process will be conducted according to the contract, including inspection of appearance, technical specifications, installation quality, and safety performance.
Subsequently, a third-party environmental testing agency will conduct emission tests under normal operating conditions. Only after three consecutive tests confirming VOCs ≤50mg/m³ can the system proceed to "final acceptance." Only after passing the acceptance test can the system be officially put into operation.